Saline Middle School Bond Update
Join us for the Saline Middle School Renovations Groundbreaking Ceremony on Thursday, March 20 at 3:30 p.m. The event will be held in the former bus maintenance garage near the Senior Center.
Progress Updates
-
Click to see a larger version Winter 2025 Athletic Complex Rendering Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Winter 2025 Senior Center Rendering Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Winter 2025 Senior Center Rendering Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Winter 2025 Senior Center Rendering Skip to end of gallery Skip to start of gallery
Summer 2025
- Classroom Technology Upgrades
- STEAM and Life Skills Classroom Renovations
- Saline Area Senior Center Expansion Begins
- Huron Valley Beauty Academy Relocation Begins
Spring 2025
- SMS Football, Tennis, Pickleball Construction Begins
- Drives and Parking Lot Construction Begins
Fall 2024
- Solar Integrated roof project completed Fall 2024
2023-2024
- SMS STEAM, Athletics, Senior Center Design Meetings
2023
- Camera/Guest Security System Upgrades Completed