Heritage School Bond Update

Winter 2024 - 25

  • Heritage - STEAM Center Design meetings

  • March 2025 Construction Starts


Fall 2024

New inclusive playground equipment and a new turf field have been installed. Soft playground surfacing and playground structures have been installed.

Summer 2024

Playgrounds Y5 - 5: Start & Complete - Completed


Winter 2024

  • Heritage - STEAM Center Design meetings

  • March 2025 Construction Starts


Summer 2023

  • Camera/Guest Security System Upgrades - Completed
     


June 2023

  • Design Considerations for the Playground Equipment

June 2023 Design Considerations for the Playground Equipment