Our community voted YES to support the 2022 Saline Area Schools bond proposal, which will provide $180,000,000 for building & site improvements to address identified facility needs. The 2022 bond millage resulted in a net tax rate decrease of 0.50 mills on summer 2023 taxes.
Any Questions?
This bond is divided up into 3, 3-year phases with each phase having $60M in construction.
Continue Design Meetings
SMS STEAM, Athletics, Senior Center
Summer 2024 Y5 - 5 Playgrounds
Construction on all 4 playgrounds Completed!
Summer 2025
HS Air Conditioning to Main Gym, Auxiliary Gym, and Locker Rooms
Spring 2025
SMS Football, Tennis, Pickleball, Drives, Parking Lots & Student Transfer Facility
Partnerships
Bond Video Links
On February 13, 2024, The Saline Board of Education approved funding for several bond-funded projects including the Operations Center, currently under construction, the High School STEAM Center and weight room additions, expected to begin construction this summer, and upgrading classroom audio/visual equipment in three buildings across the District this summer.
You can view the complete agenda, including each recommended motion, and a recording of the meeting and approvals on the Saline Board of Education website.
February 2024 - Bond Updates
November 2023 - Bond Updates
August 2023 - Board of Education Meeting - Hornets Operation Funding Approved
June 2023 - Bond Updates - Board Presentation
May 2023 - Bond Technology Aspects of Bond - Board Presentation
Bond Project Image Updates
- Click to see a larger version Hornet Operation Center Maintenance Garages and Bus Wash Continuing work Skip to end of gallery Skip to start of gallery
- Click to see a larger version Fall 2024 Hornet Operations Center Construction continuing on the Hornet Operation Center. Skip to end of gallery Skip to start of gallery
- Click to see a larger version May 2024 Hornet Operations Building in Progress Construction began in September for the new Hornet Operations Center, a new building on Tefft Court in Saline. The Hornet Operations Center will provide office space for the Transportation and Buildings and Grounds departments, bus maintenance facilities, a bus wash, and grounds and equipment storage. The relocation of the departments to the new Operations Center will allow the existing spaces at Saline Middle School to be renovated in upcoming phases of the bond implementation Skip to end of gallery Skip to start of gallery
- Click to see a larger version May 2024 High School Construction Progress Aerial view of the construction progress of the STEAM addition to the High School. Skip to end of gallery Skip to start of gallery
- Click to see a larger version March 2024 High School Ground Breaking of the STEAM Center and the Weight Room The groundbreaking event was held on March 22, at Saline High School. Construction at SHS will begin on March 25 and is expected to be an 18-month long process. Both additions are scheduled to open in August 2025. photo by Lonnie Huhman Skip to end of gallery Skip to start of gallery
- Click to see a larger version March 2024 High School Ground Breaking of the STEAM Center and the Weight Room We're so excited to see bond-funded projects coming to life at the High School beginning next week while students are away for Spring Break. Thank you to the Saline community for your support of our students and schools! Skip to end of gallery Skip to start of gallery
Bond Planning Documents & Links
Saline Area Schools Construction Updates
SAS Board of Education Meeting l Bond Project Request / Approval
SAS Board of Education Meeting I Bond Project Update
SAS Board of Education Meeting | Bond Campaign Update
SAS Board of Education Meeting | Bond Update
SAS Board of Education Meeting | Back to School Update (Slides 8-11)